Maintenance works
- Work on the Birkenwerder rectifier substation - construction of track crossings, cable work + work on the electronic signal box (Estw S1 North) - remaining cable system work
from
Friday, 11.07.2025
21:45
21:45
until
Monday, 14.07.2025
01:30
01:30
Affected train traffic
show details
Back to details
Information
- Rail replacement bus service
- Bus S1: Birkenwerder <> Oranienburg
- Please use the timetable information before starting your journey.
Details
Bus stops of the rail replacement service, Bus S1X: Birkenwerder <> Oranienburg
Station | in the / on the | Stop like |
---|---|---|
S Birkenwerder | Clara-Zetkin-Straße | replacement stop |
Birkenwerder, Kirche | additional stop in Hauptstraße | replacement stop |
Borgsdorf, Berliner Chaussee | additional stop in Berliner Chaussee | replacement stop |
S Lehnitz | Gutsplatz | replacement stop |
S Oranienburg | station square | replacement stop |
- The transport of bicycles, strollers and wheelchairs is only possible within the scope of available capacities, prams and wheelchairs have priority.
- Please purchase your tickets before starting your journey. Unfortunately, it is not possible to purchase tickets on the buses.
Bus stops of the rail replacement service, Bus S1A: Birkenwerder <> Oranienburg
Station | in the / on the | Stop like |
---|---|---|
S Birkenwerder | Clara-Zetkin-Straße | replacement stop |
Birkenwerder, Kirche | additional stop in Hauptstraße | replacement stop |
Borgsdorf, Berliner Chaussee | additional stop in Berliner Chaussee | replacement stop |
S Borgsdorf | Bahnhofsvorplatz | replacement stop |
S Lehnitz | Gutsplatz | replacement stop |
S Oranienburg | station square | replacement stop |
- The transport of bicycles, strollers and wheelchairs is only possible within the scope of available capacities, prams and wheelchairs have priority.
- Please purchase your tickets before starting your journey. Unfortunately, it is not possible to purchase tickets on the buses.